Environment (Required on creation):
Cockpit (version >= 7.12)
Description (Required on creation; please attach any relevant screenshots, stacktraces, log files, etc. to the ticket):
When activityInstanceId is NULL for a historic variable instance, then Cockpit shows a notification (Could not load scope for variables of completed process instances: too many activity instances) in "Variables" section of History view of Process Instance.
Steps to reproduce (Required on creation):
- A process instance has a process variable for which activityInstanceId is null.
- In Cockpit, go to process instance history tab
- Open variables tab
Observed Behavior (Required on creation):
- Notification is displayed that says "Could not load scope for variables of completed process instances: too many activity instances"
Expected behavior (Required on creation):
- There should not be any misleading notification in this case.
Root Cause (Required on prioritization):
Solution Ideas (Optional):
Hints (Optional):
This is the controller panel for Smart Panels app
[CAM-13880] Cockpit: Incorrect notification in History view of Variables
Link | New: This issue is related to SUPPORT-11452 [ SUPPORT-11452 ] |
Attachment | New: Screenshot 2021-08-27 at 14.23.01.png [ 45513 ] |
Description |
Original:
h4. Environment (Required on creation):
Cockpit (version >= 7.12) h4. Description (Required on creation; please attach any relevant screenshots, stacktraces, log files, etc. to the ticket): When activityInstanceId is NULL for a historic variable instance, then Cockpit shows a notification ({{Could not load scope for variables of completed process instances: too many activity instances}}) in "Variables" section of History view of Process Instance. h4. Steps to reproduce (Required on creation): * A process instance is already completed, has more a single activity instance and a single process variable. * In Cockpit, go to process instance history tab * Open variables tab h4. Observed Behavior (Required on creation): * Notification is displayed that says "Could not load scope for variables of completed process instances: too many activity instances" h4. Expected behavior (Required on creation): * There should not be any misleading notification in this case. h4. Root Cause (Required on prioritization): h4. Solution Ideas (Optional): h4. Hints (Optional): |
New:
h4. Environment (Required on creation):
Cockpit (version >= 7.12) h4. Description (Required on creation; please attach any relevant screenshots, stacktraces, log files, etc. to the ticket): When activityInstanceId is NULL for a historic variable instance, then Cockpit shows a notification ({{Could not load scope for variables of completed process instances: too many activity instances}}) in "Variables" section of History view of Process Instance. h4. Steps to reproduce (Required on creation): * A process instance is already completed, has more a single activity instance and a single process variable. * In Cockpit, go to process instance history tab * Open variables tab h4. Observed Behavior (Required on creation): * Notification is displayed that says "Could not load scope for variables of completed process instances: too many activity instances" !Screenshot 2021-08-27 at 14.23.01.png|thumbnail! h4. Expected behavior (Required on creation): * There should not be any misleading notification in this case. h4. Root Cause (Required on prioritization): h4. Solution Ideas (Optional): h4. Hints (Optional): |
Mentioned Roles |
Mentioned Groups |
Description |
Original:
h4. Environment (Required on creation):
Cockpit (version >= 7.12) h4. Description (Required on creation; please attach any relevant screenshots, stacktraces, log files, etc. to the ticket): When activityInstanceId is NULL for a historic variable instance, then Cockpit shows a notification ({{Could not load scope for variables of completed process instances: too many activity instances}}) in "Variables" section of History view of Process Instance. h4. Steps to reproduce (Required on creation): * A process instance is already completed, has more a single activity instance and a single process variable. * In Cockpit, go to process instance history tab * Open variables tab h4. Observed Behavior (Required on creation): * Notification is displayed that says "Could not load scope for variables of completed process instances: too many activity instances" !Screenshot 2021-08-27 at 14.23.01.png|thumbnail! h4. Expected behavior (Required on creation): * There should not be any misleading notification in this case. h4. Root Cause (Required on prioritization): h4. Solution Ideas (Optional): h4. Hints (Optional): |
New:
h4. Environment (Required on creation):
Cockpit (version >= 7.12) h4. Description (Required on creation; please attach any relevant screenshots, stacktraces, log files, etc. to the ticket): When activityInstanceId is NULL for a historic variable instance, then Cockpit shows a notification ({{Could not load scope for variables of completed process instances: too many activity instances}}) in "Variables" section of History view of Process Instance. h4. Steps to reproduce (Required on creation): * A process instance has a process variable for which activityInstanceId is null. * In Cockpit, go to process instance history tab * Open variables tab h4. Observed Behavior (Required on creation): * Notification is displayed that says "Could not load scope for variables of completed process instances: too many activity instances" !Screenshot 2021-08-27 at 14.23.01.png|thumbnail! h4. Expected behavior (Required on creation): * There should not be any misleading notification in this case. h4. Root Cause (Required on prioritization): h4. Solution Ideas (Optional): h4. Hints (Optional): |
Mentioned Roles |
Mentioned Groups |
This ticket was migrated to github: https://github.com/camunda/camunda-bpm-platform/issues/2572. Please use this link for any future references and continue any discussion there.