      Context:

      Once OPT-2587 is done, we can add a migration to apply the new work and idle duration calculation logic to existing usertasks.

      Depending on the effort, we could also include OPT-5024 in this migration.

       

      AT:

      • There is a migration that recalculates all uesrtask work and idle durations
      • (Optional) the migration also removes the claimDate field

        This is the controller panel for Smart Panels app