In Cockpit, I cannot see number of finished and canceled activity instances on nested activities

XMLWordPrintable

      Steps to reproduce:

      1. deploy a process that contains at least one embedded subprocess with at least one user task inside
      2. start multiple process instances of this process (for example three)
      3. complete one of the nested user tasks
      4. login into Cockpit
      5. go to Process Definition Historic View

      Observed Behavior:

      • The nested activities do not have the number of finished and canceled activity instances.

      Expected Behavior:

      • The nested activities have the number of finished and canceled activity instances.

      Hint:

      • The number of finished and canceled activity instances are only show for "top level" activities.

        This is the controller panel for Smart Panels app

              Assignee:
              Michael Schoettes
              Reporter:
              Roman Smirnov
              Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

                Created:
                Updated:
                Resolved: