Type:
Feature Request
-
Resolution: Done
-
Priority:
L3 - Default
-
Affects Version/s: None
- given:
- There is data with running and completed user tasks in the engine or potentially other running/completed flow nodes
- This data is imported into Optimize
UserTasks:
- when:
- I create a report with user task: duration view (and whatever visualization/grouping, etc)
- then:
- I see results for all user tasks (the running and completed ones)
- It is possible to change the configuration to either show user tasks that are running, completed or all
- such that:
- I can compare running and completed user tasks
FlowNodes:
- when:
- I create a report with flownode: duration or count view (and any visualization/grouping)
- then:
- I see results for all flow nodes (running + completed)
- It is possible to change the configuration to either show flownodes that are running, completed or all
- such that:
- I can compare running and completed flownodes
Additional Infos:
New property: flowNodeExecutionState in configuration field of the report. Can have the values completed, running and all
User Interface:
See attachments for screendesign
This is the controller panel for Smart Panels app
1.
|
Allow usertask/flownode control with execution state |
|
Done | Unassigned |
2.
|
Refactor report duration evaluation results |
|
Done | Unassigned |
3.
|
Change duration evaluation results to refactored result structure |
|
Done | Unassigned |
4.
|
Running FlowNode/UserTasks duration calculation |
|
Done | Unassigned |
5.
|
Running/completed/all execution state control for usertask/flownode reports |
|
Done | Unassigned |
6.
|
Import running UserTasks |
|
Done | Unassigned |
7.
|
Deliver screen design for task selection |
|
Done | Andreas Geier |
8.
|
Upgrade considers added claimDate field for imported completed user tasks |
|
Done | Unassigned |